Templates / Groundworks and drainage

Excavation inspection

Checklist · Start of every shift, and after anything that could affect its strength or stability

The excavation inspection report CDM 2015 requires: at the start of each shift, after an event affecting its stability, and after any accidental fall of rock or earth.

Use it in Sitro: add it to a project and fill it on a phone, free for 14 days.

The law and guidance behind it

The questions

The inspection

  1. Inspection carried out for (name) (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(i))
  2. Their address (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(i))
  3. Where the excavation is (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(ii))
  4. Description of the excavation (depth, support, plant and materials near it) (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(iii))
  5. Date and time of the inspection (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(iv))

Checks

  1. Sides supported or battered back, no signs of collapse
  2. Edge protection or barriers in place
  3. Spoil and materials kept back from the edge
  4. Safe way in and out (ladder secured)
  5. No water build-up; pumping in hand
  6. Buried services located and protected
  7. Air safe where people work below ground
  8. Plant stops kept back from the edge
  9. Result

Findings and sign-off

  1. Anything found that could put anyone's health or safety at risk (write "None" if nothing) (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(v))
  2. Action taken because of it (write "None" if none needed) (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(vi))
  3. Further action needed (write "None" if none) (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(vii))
  4. Inspected by (name) (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(viii))
  5. Their position (Construction (Design and Management) Regulations 2015, Regulation 24(1)(b)(viii))
  6. Signature of the person making the report

A template to adapt to your site, not legal advice.

More groundworks and drainage templates